REC Power Development and Consultancy Limited (RECPDCL), a wholly owned subsidiary of REC Limited, has handed over Vikramshila Power Transmission Limited, a project-specific Special Purpose Vehicle (SPV), to Adani Energy Solutions Limited (AESL). The SPV has been established for Bihar’s Pirpainti power evacuation project.
The handover took place on November 21, 2026, following AESL’s selection as the successful bidder through the Tariff Based Competitive Bidding (TBCB) process conducted by RECPDCL. The project will be developed on a Build, Own, Operate and Transfer (BOOT) basis.
AESL Selected Through Tariff-Based Competitive Bidding
RECPDCL served as the Bid Process Coordinator for the competitive bidding process. The SPV was formally handed over by Ratnesh Kumar, General Manager (TBCB), RECPDCL, to Shashank Sharma, Chief Business Development Officer (CBDO), Adani Energy Solutions Limited.
Officials from RECPDCL, AESL and Bihar State Power Transmission Company Limited (BSPTCL) were present during the handover.
The SPV will facilitate the development of Bihar’s intra-state transmission project titled “Evacuation of Power from 3×800 MW STPP Pirpainti”. Its transfer marks the next stage in developing the transmission infrastructure required to evacuate electricity from the upcoming power project.
Four GIS Substations Planned Under Bihar Transmission Project
The project envisages four GIS substations at different locations in Bihar, along with associated high-voltage transmission lines. The proposed substations are:
| Location | Proposed substation |
|---|---|
| Jhanjharpur, Madhubani | 400/220/132 kV GIS GSS |
| Bethauli, Darbhanga | 220/132/33 kV GIS GSS |
| Begusarai | 400/220 kV GIS GSS |
| Begusarai (New) | 220/33 kV GIS GSS |
The project will also include associated 400 kV, 220 kV and 132 kV transmission lines to facilitate power evacuation and strengthen Bihar’s intra-state transmission network.
Pirpainti Project to Support Bihar’s Power Transmission Network
The transmission project is designed to support the evacuation of electricity from the 3×800 MW Pirpainti Super Thermal Power Project. The planned substations and transmission lines will form an important part of the infrastructure connecting the generating project with the state’s electricity network.
The handover of Vikramshila Power Transmission Limited to AESL enables the successful bidder to take forward the project under the BOOT framework. The development is an important step towards establishing the transmission infrastructure required for power evacuation from the Pirpainti thermal power project.